SMEX Site Visit Schedule

SMEX Study Teams -

Thank you for your input on adjustments to the SMEX downselect process. The due date for Concept Study Reports remains unchanged: June 18, 2004. I do not yet have the revised cost/schedule guidelines that can be supported by the President's FY05 budget request for the Explorer program. I will provide those as soon as possible.

Based on your preferences, Carlos and I have put together following the site visit schedule. Since these dates were pre-approved, no changes are expected.

Paul Hertz
Explorer Program Scientist


SMEX Downselect Page

NASA Headquarters Responsible Office: Code SZ
Last Updated: 11 February 2004
Author: Paul Hertz (Code SZ)